Indian Army
Overclocking Capacity
Winter Thermals

OVERVIEW
Achieved the highest ever MPC in the industry by supplying 300,000 Garments per month consistently over 5 months.
High volume order coupled with a tight deadline to enable personnel protection during the upcoming winter season, leading to needing to augment manufacturing capabilities to an unprecedented scale. Garment capacity was ramped up to 300% in a very short time by employing a 24×7 production schedule and managing downtime very diligently with ample provisions of redundancy, including that for raw material sourcing which could cater to such high turnover.
We supplied 1.5 Million garments in a period of 5 months, including 60 acceptance visits by inspectors and random sampling of a product during the same period. The entire order was delivered within 80% of the delivery lead time otherwise allotted to us.
To know more about this project or if you have a similar project for us to collaborate with?
- The monthly production capacity of 300,000 Garments per month achieved
- Production capacity ramped up 300% within a short time
- 60 QC visits by officers within 5 months
- 5 million Garments delivered within 5 months
- The monthly production capacity of 300,000 Garments per month achieved
- Production capacity ramped up 300% within a short time
- 60 QC visits by officers within 5 months
- 5 million Garments delivered within 5 months
OVERVIEW
Achieved the highest ever MPC in the industry by supplying 300,000 Garments per month consistently over 5 months.
High volume order coupled with a tight deadline to enable personnel protection during the upcoming winter season, leading to needing to augment manufacturing capabilities to an unprecedented scale. Garment capacity was ramped up to 300% in a very short time by employing a 24×7 production schedule and managing downtime very diligently with ample provisions of redundancy, including that for raw material sourcing which could cater to such high turnover.
We supplied 1.5 Million garments in a period of 5 months, including 60 acceptance visits by inspectors and random sampling of the product during the same period. The entire order was delivered within 80% of the delivery lead time otherwise allotted to us.
To know more about this project or if you have a similar project for us to collaborate with?